
The White River Hydroelectric Power
project is located near Batesville, Arkansas. Batesville is the second
oldest municipality in the state of Arkansas, after Georgetown. It was
named for James Woodson Bates who settled in the town and was the first
territorial delegate from Arkansas to the Congress of the United States.
Batesville has also gone by the names of Napoleon and Polk Bayou.
In early days, Batesville was an
important port on the White River and served as an entry point to the
interior of northern Arkansas. Batesville played a large role in the
settling of the Ozark Mountains region and served as the central land
office for northern Arkansas.
The first known settlement of the
Batesville area was in 1810 near the mouth of Polk Bayou, and by 1819
the town had a ferry across the White River and about a dozen houses.
The town was partially laid out in early 1821, and on March 3, 1822 a
bill of assurance was recorded and executed and the town's plat was laid
out. Batesville became the county seat in 1821. In January 1822, Judge
Richard Searcy opened the town's first state circuit court. The town's
first post office was established in 1822, and in 1830 became the home
of a county court. On 25 September 1836, shortly after Arkansas was
granted its statehood, Governor Conway incorporated Batesville Academy,
the state's first academy. In the past, the area in and around the city
had extensive quarries of manganese ore, phosphate rock, sandstone,
limestone, and marble. Currently Arkansas Lime owns and operates a lime
kiln nearby and there are a few limestone quarries operating in the
area.
A major event
occurring around the turn of the century was the beginning of
construction of three locks and dams to make White River navigable above
Batesville. According to the U. S. Army Corps of Engineers, the River
and Harbors Act of March 1899, authorized ten fixed dams with concrete
locks between Batesville and Buffalo Shoals. Three of these locks and
dams were completed; No. 1 at Batesville and Nos. 2 and 3 up the river
from the town. Lock and dam No. 1 was placed into operation October 16,
1903, and the other two were not far behind, but while construction was
going on, the railroad began building the White River Division which
paralleled the river to Cotter. The railroad with through connections
offered better service and the lock and dam project was dropped after
No. 3 was finished. However, the government maintained the three which
were built until 1951.
After the locks and dams were taken
out of service they were sold by the U. S. Army Corps of Engineers for
private ownership. This is the only time in the history of the United
States that this had ever been done. Eventually Independence County
acquired ownership of all three of them and plans were made to convert
the old locks into hydro-electric generating stations.
Architects went to
work on designing the generators and in April 2004 Mobley Contractors,
Inc. was awarded the contract and began construction. Work started on
site #3 located near Marcella, Arkansas. The lock structure was too
deteriorated at that location so a new site was excavated to the side of
the White River. When the powerhouse was constructed channels were
excavated up and downstream of the structure to allow water in and out
of the generator. The sides of the channel were line drilled on one foot
centers to limit rock breakage beyond the excavation limits and up to 20
feet of rock was precision drilled and blasted out for construction of
the powerhouse and the water channels.
The generator at Site #2, near
Desha, Arkansas was constructed within the lock itself. The lock
underwent significant modification and reinforcement construction in
order to contain the new powerhouse. Rock excavation in bottom of the
lock was necessary in order to achieve grade depth for the powerhouse.
There was also some underwater rock excavation in the upstream channel
in order to allow water in and out of the generator.
The concrete
upstream gate sill, water intake manifold and front entry sill were part
of the original lock construction and had to be removed from within the
lock without any damage to the existing structure to remain. This phase
of the project was achieved with precision controlled drilling and
blasting techniques designed to fragment the concrete to be removed
while leaving the remainder of the lock undamaged.
The
generator at site #1, located in Batesville, Arkansas was the most
challenging by far. This lock required up to twenty two feet of rock
excavation below the bottom of the lock walls inside the structure. This
work was complicated by a number of factors. The sheer volume of rock
that was required to be removed which was in direct contact with the
footings of the existing lock to remain, the close proximity of an open
restaurant overlooking the entire project within sixty feet of the
closest rock excavation, a thirty inch above ground wastewater sewer
main less than twenty feet from the closest rock excavation and only ten
feet from the pristine White River, boat traffic and interested
pedestrians present at all times.
This lock also had the concrete
sills and the water intake manifolds which obstructed the water flow
into the powerhouse. These concrete structures had to be removed but
with an addition level of difficulty. The logistics of this location
required that these be removed with the lock and powerhouse already
watered up. The precision concrete removal had to be done underwater.
Once the required concrete demolition was finished, an additional two to
eight feet of rock had to be excavated below the bottom of the concrete
sills on a 6 to 1 slope to allow the water unimpeded and down slope flow
into the powerhouse water intake.
The upstream end had some minor
underwater rock excavation which had to be performed in a maximum of
thirty seven feet of water. The downstream end of the lock structure had
to be excavated from twenty two feet below the bottom of the existing
lock walls on a 6 to 1 slope going downriver and fanning out into the
main river channel on a 45 degree angle. All of this drilling and
blasting was performed underwater.
This challenging three year project
was successfully finished on time and with no lost time accidents. The
hydro-electric generators are now in full operation. Dykon Blasting
would like to give grateful acknowledgment to Mobley Contractors, Inc
for their trust and support during this difficult project. Their
professionalism and attention to safety, detail and work coordination
was unequaled in the industry. We hope to work with them on projects in
the future. |