|
| |

Precision Drilling &
Blasting |
Reinforced Concrete
Demolition Drilling and Blasting |
|
Coldwater
Creek
Photo Album |
Blasting at the Central California Power Agency
Geothermal Plant #1
 |
On August 7, 2000,
work began on the blasting of the Coldwater Creek turbine / generator
pedestals in the Central California Power Agency Plant #1, located near
Kelseyville, CA., in a region known as "The Geysers." The plant was built in 1988 and operated
until it was decommissioned in 1994 because of inefficiency in
its operation.
The Coldwater Creek generator facility was a dry
steam geothermal power plant. Work is currently underway to remove
the power plant and restore the area around it to the original state prior
to construction.
|
| What is Geothermal
Energy?
Geothermal energy is renewable heat energy from deep in the earth.
Heat is brought to the near-surface by thermal conduction and by
intrusion into the earth's crust of molten magma originating from great
depth. Ground water is heated to form hydrothermal resources --
naturally occurring hot water and steam. Use of hydrothermal energy is
economic today at a number of high-grade sites. Hydrothermal resources
are tapped by existing well-drilling and energy-conversion
technology to generate electricity or to produce hot water for direct
use. Earth energy is used by geothermal heat pumps. Hot dry
rock, magma and geopressured geothermal energy have enormous potential.
For generation of electricity, hot water, at temperatures ranging
from about 300deg.F to more than 700deg.F, is brought from the
underground reservoir to the surface through production wells, and is fed to a turbine engine, which turns a
generator. Spent geothermal fluid is injected back into peripheral parts
of the reservoir to help maintain reservoir pressure. |
|
 |
Plant Reclamation of
Richmond, California is heading up the demolition project. The
Company's president, Bill Glueck, decided that blasting these huge
foundations was the best way to remove them.
Dykon Blasting was then contracted to assist Plant
Reclamation in the demolition of the foundations.
On Monday, August 7, 2000, Dykon began drilling the
blast holes in the steel reinforced concrete foundations. Once this
has been done, the equipment inside the generator building will be removed
from around the foundations leaving them in place with the generators
still resting on top of them.
|
|
The building itself was left in place until after the
foundations are blasted. This is being done to prevent concrete from
the foundations being sprayed out into the surrounding area and left in
the environment. Every effort is being made to restore the area to
it's original state.
When all the equipment inside the powerhouse was removed and
nothing remained but the generators and turbines on the pedestals, Dykon
Blasting returned to the project to explosively demolish the pedestals.
|
|
 |
These reinforced concrete
turbine foundations were designed to earthquake standards. The goal
of the blasting was not only to fragment the concrete, but to bring the
half million pound steam turbine / generators down to a point where they
could be safely removed.
The legs of the foundation would have to be
completely blasted out from under the units in order for them to
fall. On November 10th, 2000, Dykon test blasted the heaviest of the
center columns on the far west foundation.
Because of the earthquake resistant design, Dykon
loaded the concrete in the test column at twice the amount of explosive
that would normally be required to blast reinforced concrete. |
| The picture above clearly
shows that this is no ordinary reinforced concrete. The concrete in
the column was fragmented but the reinforcing steel held it
together. These columns had to be completely removed in order for
the turbines to fall.
A second test column was loaded and shot the same
day. The picture to the right shows that this was a successful
test. Dykon, with the help of Plant Reclamation would now move
forward with the production blasting. |
 |
 |
The first foundation was
loaded and shot Saturday morning, November 11th. 1205 pounds of
explosive was loaded into 110 blastholes.
The second foundation was loaded with just under 1400
pounds of explosive in 110 blastholes and was blasted late the same
afternoon.
Our online photo album shows more pictures of the
blasted foundations. |
| We at Dykon Blasting would like to
express our thanks to Plant
Reclamation for helping make this project a successful one.
Their cooperation and assistance made it all possible. A special
thanks goes out to Bill, Nick and Jose who were onsite with us throughout
the blasting. |
Some of the images used on this page are actual progress
construction photos on loan to Dykon and used with the permission of Plant
Reclamation. You can see all of them in our online
photo album slide show. These photos are the property of Central
California Power Agency and Plant Reclamation. Please do not take
them without permission. Thank you for your understanding.
Relevant
Links:
Our online Photo
Album | Plant
Reclamation
Geothermal
Energy Slide Show | Geothermal
Glossary of Terms
|