A Precision Drilling and Blasting Company        

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 

 
 
 
 


 Precision Drilling & Blasting

Dykon Blasting
Abitibi, Consolidated
Snowflake, Arizona

Reinforced Concrete Demolition

Drilling and Blasting Reinforced Concrete
A picture of the entrance to the plant property early in the morning before the sun came up.Abitibi Consolidated owns and operates a papermill near Snowflake, Arizona.  Built in the early 1960's this papermill processed wood into pulp and manufactured paper for use nationwide.

The paper mill changed ownership from its original builders.  As the years progressed, more emphasis has been placed on recycling of paper rather than the manufacture of new.  The United States Government subsidizes recycling to a large degree in order to preserve our forests and woodlands.  

Abitibi Consolidated recently took over ownership of the Snowflake Plant and part of the terms of the sale was that the plant would be operated as a 100% recycled paper mill.  All of the equipment inside the plant that processed raw wood products into paper had to be removed.

A picture of all eight foundations taken from the west end.  You can see the overhead pipe racks in the background behind the furthest foundations east.Louisiana Chemical Dismantling was contracted to remove this portion of the Abitibi Consolidated Paper mill and has been working inside the operational plant for several months.  Part of the scope of work was to demolish and remove some large reinforced concrete rotary kiln foundations.  These foundations were located inside the operational facility and had to be removed without disturbing any of the surrounding manufacturing processes within the plant.   Some of the operational plant equipment was so close that the foundations had to be "Demolished in Place."  

Louisiana Chemical Dismantling contracted with Dykon Blasting to assist them with the tricky explosive demolition of these concrete foundations.  Dykon Blasting arrived onsite on October 2, 2000 and began preparing the foundations for explosive demolition.

The number 7 pier being covered for the blast.  The explosives are loaded into the foundation and it is ready to be blasted.  This foundation was the second closest one to the overhead piperack and several storage tanks.Blasting is not an everyday occurrence within an operational manufacturing facility.  Coordination of the demolition and routine plant activities had to be arranged so that both operations could be unaffected by the activities of the other.  Safety was the top priority.  The foundations would have to be covered for the blasting to protect nearby lives and property within the plant.  Personnel working inside the plant had to be made aware of the impending blasts and the work zone around the foundations had to be barricaded off to prevent access of people into the blast area while the demolition work was taking place.

The drilling of the blast holes into all eight of the concrete foundations for placement of the explosives took three days to finish.  On the fourth day, the number 5 foundation was blasted.   A foundation within the center of the eight was chosen to blast first because it was surrounded by the rest and by doing so, Dykon took advantage of the additional protection provided by the other foundations which would be demolished later.

The protective cover is being removed from the blasted pier.  The concrete is completely crushed and nothing was thrown from the area.All eight foundations were loaded, covered and shot in three days.  The entire project took 6 days to complete.  No blasting project like this one can be successful without the cooperation and teamwork of everybody involved.  Louisiana Chemical Dismantling and the Abitibi Plant personnel worked exhaustively with us towards that end and we appreciated their efforts greatly.   It's an awesome sight to behold when everybody works together to get the job done and this project was a perfect example of that.   A world of thanks goes out from Dykon to Louisiana Chemical Dismantling and Abitibi Consolidated for their professional cooperation on the successful completion of the explosive demolition of the reinforced concrete piers inside the Snowflake Paper mill.


 

 

See our Online Photo Album of the project

See video clips of the blasting

Louisiana Chemical Dismantling Co., Inc.
24 27th Street
Kenner, Louisiana  70062
(504) 464-0770

Abitibi Consolidated
Snowflake Division
P.O. Box 128
Snowflake, Arizona  85937
(520) 536-9347
 



Safety & Ethics | Contact Projects | Work History | Links | Quick Reference
FAQ's | Site Map | Video Clips | Home

***  Rock Blasting Services  ***
Quarry Shot Service
| Rock Blasting | Contract Drilling
Road Cuts | Utility Blasting | Sitework
Precision Controlled Rock Blasting


Site Created and Maintained by Dykon Blasting Corp.
For use with Internet Explorer 6 or later.
© 1999-2007 Dykon Blasting Corp.
Email WebMaster

A Precision Drilling and Blasting Contractor